November-December 2009

Restoring a Link to Nature

On the fast track with South Los Angeles Wetlands Park

Article Tools

Create a Link to this Article

This Avalon Boulevard area in South Los Angeles will be transferred into a wetland park.

Additional Article Content

By David C. Richardson

Comments


Besides the lack of information, the site presented a few other drawbacks. “There were rail spurs, because they’ve been doing maintenance in that area,” says Vargas, which could have resulted in surface contamination. He anticipates there will a need for be some remediation, particularly “taking out some of the soils that may be adjacent to some of the clarifiers.”

 He also notes, “There’s always that little twinge, when you’re dealing with a brownfield site—it’s the unknowns that could get you. That’s why we’ve done all this exhaustive preliminary design report work, to try and know as much about that as we can.”

To cap off its investigations, Psomas brought in a subsurface detection unit to probe the underground terrain and validate what it had learned. According to Vargas, the survey uncovered nothing particularly alarming. Nonetheless, as part of the project’s collaborative arrangement, the MTA committed $900,000 for site remediation and cleanup. Council member Perry says, however, she is hopeful that some of the remaining rail artifacts could be preserved to find a second life as historic design elements for the future park, while some of the antiquated structures might be rehabbed for use as public space.

Photo: Psomas
Artist’s rendition of the South Los Angeles Wetland Park
Photo: Psomas
The park will feature trails, boardwalks, and observation decks.

Monitoring the storm drain at San Pedro Street adjacent to the Wetland Park project, Psomas was able to confirm, during a particularly dry season of September 2007, an average flow of approximately 14,000 gallons per day (gpd), a quantity of water that Vargas says would be sufficient to sustain the wetland habitat during periods between rains.

Target Funding
In addition to the $900,000 the MTA plans to contribute for site remediation, Psomas estimates the total project cost at about $24 million. Assembling this funding, Perry says, has been the toughest challenge in putting together the wetland project.

A recent bond issue, Proposition O, is expected to provide $8 million, but the balance must be stitched together from wherever the money can be found. “Some of it’s grant money, some of it’s brownfields money; it just depends,” says Perry.

According to John Saldin, senior civil engineer with the Los Angeles Department of Public Works, the initiative is being funded via numerous sources, including a Baykeeper settlement; Proposition K, which targets park improvements through a competitive grant process; Proposition 50, which focuses on protecting drinking water supplies; and Proposition 40, a measure broadly targeting air, water, parks, and resource protection.

As project manager for the South Los Angeles Wetlands, Saldin says the cooperation between various agencies involved in the project has been key in overcoming the funding hurdles. “We interact with a number of other groups in the city. They are the grant holders, but we provide them with the documentation to get the grant money.”

But according to Vargas, Proposition O has been the key measure facilitating the effort. Had it not been for the passage of Proposition O in 2004, authorizing the city to issue up to $500 million in bonds for “green stormwater solutions,” Vargas says, getting the wetlands project started “would have been an uphill battle.”

He explains, “I’m working on a number of projects for other municipalities, for nonprofits that are real advocates for sustainable stormwater solutions, and without a measure like Proposition O, the money is really not there. You’ve got to get people excited about it generally to get a donor.

“Some of the backing that the council member wields is the ability to round up the funding and get the project going,” says Saldin. “It takes some coordination, but once it’s all lined up and each group knows what it needs to do, then we just do it.”

And they are making progress. With the property transfer yet to be finalized, and with time still to go before the Bureau of Sanitation finally takes occupancy of the site, design work is already more than 50% complete. Next Page >

Advertisement

What Do You Think?

Post a Comment

Be the first to tell us what you think!

Post a Comment

Not a subscriber? Sign Up
 
 
*  
 




 

Get Stormwater E-mail Updates!

Get weekly news and updates through our Stormwater e-mail newsletter!